At which point does crashing of a project cease?


A) When the project is completed
B) When no additional crashing is possible
C) When the cost to crash equals or exceeds the benefit of crashing
D) All of the choices are correct
E) None of the choices are correct

F) None of the above
G) D) and E)

Correct Answer

verifed

verified

The critical path has zero path slack time.

A) True
B) False

Correct Answer

verifed

verified

A project manager usually staffs the human resources required for a project by hiring outside specialists that only work for the company for the duration of the project.

A) True
B) False

Correct Answer

verifed

verified

An activity,A,has two succeeding activities,B and C.Given the following information,determine the latest starting time for activity A. EF B = 15,EF C = 17,LF B = 24,LF C = 27; activity times are A = 4,B = 6,C = 8.


A) 14
B) 15
C) 16
D) 17
E) 18

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

One way that project management differs from management of more traditional operations is the limited time frame of projects.

A) True
B) False

Correct Answer

verifed

verified

A hierarchical listing of what must be done during a project is called a project matrix.

A) True
B) False

Correct Answer

verifed

verified

Project managers bear the ultimate responsibility for the success or failure of the project.

A) True
B) False

Correct Answer

verifed

verified

  -What are the estimated standard deviations (in weeks)of the durations for activities A-H? -What are the estimated standard deviations (in weeks)of the durations for activities A-H?

Correct Answer

verifed

verified

2; 1.67; 2...

View Answer

Companies that are organized as pure project organizations are equivalent to matrix organizations that temporarily group specialists from different departments.

A) True
B) False

Correct Answer

verifed

verified

Activity D has an optimistic duration of 3 days,a pessimistic duration of 9 days,and a most likely duration of 4 days.Determine its expected duration and variance.

Correct Answer

verifed

verified

te = (t0 + 4tm + tp)/6 =...

View Answer

  Given the portion of the network shown above,based on the activity durations shown what is the latest start time of activity 7 if the latest finish of activity 8 is 26,and the latest finish of activity 9 is 23? A)  18 B)  17 C)  13 D)  12 E)  10 Given the portion of the network shown above,based on the activity durations shown what is the latest start time of activity 7 if the latest finish of activity 8 is 26,and the latest finish of activity 9 is 23?


A) 18
B) 17
C) 13
D) 12
E) 10

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

The critical path for the network shown is:


A) a-c-g.
B) a-d-f-g.
C) a-d-h-i.
D) b-e-f-g.
E) b-e-h-i.

F) B) and D)
G) A) and D)

Correct Answer

verifed

verified

If two consecutive activities on the same path each have two days of activity slack,this means that each of them can be delayed by two days without delaying the overall project.

A) True
B) False

Correct Answer

verifed

verified

Activity 4 in a network diagram has an optimistic duration estimate of 5 days,a most likely duration estimate of 7 days,and a pessimistic duration estimate of 10 days.The expected duration of Activity 4 is:


A) 5
B) 6
C) 7
D) 8
E) 9

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Which of the following would probably not involve the use of project management?


A) Planning and constructing a new city hall
B) Developing a marketing campaign for the launch of a new product
C) Designing and constructing a subway system
D) Scheduling workers and purchasing raw materials for a manufacturing plant
E) Producing and staging a music festival

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Sequential dependencies among project activities are less important than the time required to complete activities.

A) True
B) False

Correct Answer

verifed

verified

What is the estimated expected (mean) duration for activity E?


A) 91 days
B) 99 days
C) 100 days
D) 101 days
E) 115 days

F) A) and D)
G) A) and E)

Correct Answer

verifed

verified

PERT was originally developed for military planning in the 1940's during the Second World War (WWII).

A) True
B) False

Correct Answer

verifed

verified

The sum of activity durations of the longest path in a network indicates expected project completion time,and the activities on it are called the critical activities.

A) True
B) False

Correct Answer

verifed

verified

The task of identifying risks should involve everyone associated with the project.

A) True
B) False

Correct Answer

verifed

verified