Filters
Question type

Study Flashcards

Using the product tree shown, determine the following: (A) The quantity of component K that will be needed to assemble 80 units of P, assuming no on-hand inventory of any components exists. (B) The quantity of component K needed to assemble 80 units of P, given on-hand inventory of 30 As, 50 Bs, and 20 Cs. [Add closing parens in figure where needed.] Using the product tree shown, determine the following: (A) The quantity of component K that will be needed to assemble 80 units of P, assuming no on-hand inventory of any components exists. (B) The quantity of component K needed to assemble 80 units of P, given on-hand inventory of 30 As, 50 Bs, and 20 Cs. [Add closing parens in figure where needed.]

Correct Answer

verifed

verified

(A) [3 Ks per C × 2 Cs per A × 2 As per ...

View Answer

The inventory records contain information on the status of each item by time period.

A) True
B) False

Correct Answer

verifed

verified

Which one of the following most closely describes net material requirements?


A) gross requirements - amount on hand - scheduled receipts
B) gross requirements - planned receipts
C) gross requirements - order releases + amount on hand
D) gross requirements - planned order releases
E) gross requirements - amount on hand + planned order releases

F) B) and D)
G) D) and E)

Correct Answer

verifed

verified

The term pegging refers to identifying the parent items that have generated a given set of material requirements for a part or subassembly.

A) True
B) False

Correct Answer

verifed

verified

Net requirements equal gross requirements minus safety stock.

A) True
B) False

Correct Answer

verifed

verified

Load reports show capacity requirements for departments or work centers which may be more or less than the capacity available in that work center.

A) True
B) False

Correct Answer

verifed

verified

The bill of materials indicates how much material will be needed to produce the quantities on a given master production schedule.

A) True
B) False

Correct Answer

verifed

verified

A regenerative MRP system is one that is updated continuously, every time there is a schedule change.

A) True
B) False

Correct Answer

verifed

verified

The bill of materials contains information on lead times and current inventory position on every component required to produce the end item.

A) True
B) False

Correct Answer

verifed

verified

Which is true of a net-change system?


A) It is a batch-type system which is updated periodically.
B) It is usually run at the beginning of each month.
C) The basic production plan is modified to reflect changes as they occur.
D) It is used to authorize the execution of planned orders.
E) It indicates the amount and timing of future changes.

F) A) and D)
G) B) and C)

Correct Answer

verifed

verified

Which of the following most closely describes dependent demand?


A) demand generated by suppliers
B) estimates of demand using regression analysis of independent variables
C) derived demand
D) demands placed on suppliers by their customers
E) net material requirements

F) C) and E)
G) C) and D)

Correct Answer

verifed

verified

The development and application of MRP depended upon two developments: (1) the recognition of the difference between independent and dependent demand, and (2) :


A) computers.
B) development of the EOQ model.
C) inventory control systems.
D) blanket purchase orders.
E) the Internet.

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

MRP is used within most MRP II and ERP systems.

A) True
B) False

Correct Answer

verifed

verified

Which one of the following most closely describes the MRP approach that is used for components or subassemblies to compensate for variations in lead time?


A) pegging
B) safety stock
C) increased order sizes
D) safety time
E) low-level coding

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Net requirements for component J are as follows: 60 units in week 2, 40 units in week 3, and 60 units in week 5. If a fixed-period, two-period lot-sizing method is used, what will be the quantity of the first planned receipt?


A) 60 units
B) 120 units
C) 180 units
D) cannot be determined
E) none of the choices

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Which of these items would be most likely to have dependent demand?


A) Xbox batteries
B) toy trains
C) flowers
D) chocolate chip cookies
E) wrist watches

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

In MRP, the gross requirements of a given component part are calculated from:


A) net requirements + amount on-hand.
B) gross requirements of the immediate parent.
C) planned orders of the end item.
D) net requirements of end item.
E) planned orders of the immediate parent.

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

Develop a material requirements plan for end item P and its components, given the following tree. Assume that all lead times are one week, and that lot-for-lot ordering is used except for item F, which is ordered in multiples of 400 units. One hundred units of P should be available at the start of week 4 and at the start of week 8. Beginning inventories are: 20 Ps, 100 As, and 200 Fs. Scheduled receipts are: 800 Fs at the start of week 1. Develop a material requirements plan for end item P and its components, given the following tree. Assume that all lead times are one week, and that lot-for-lot ordering is used except for item F, which is ordered in multiples of 400 units. One hundred units of P should be available at the start of week 4 and at the start of week 8. Beginning inventories are: 20 Ps, 100 As, and 200 Fs. Scheduled receipts are: 800 Fs at the start of week 1.

Correct Answer

verifed

verified

\[\begin{array} {c}
{ \text { Planned O...

View Answer

Scheduled receipts differ from planned receipts in that scheduled receipts:


A) have longer lead times.
B) involve orders that have not yet been placed.
C) have not been pegged with actual customer orders.
D) involve orders that have already been placed.
E) involve exceptions to order quantity policies.

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot) , and quantities on hand:  Deluxe Easter Basket BOM  Lead Time  On-Hand  Deluxe Easter Basket 1 week 10 Dark Chocolate Truffles (2 per)  2 weeks 30 Carved Chocolate Eggs (4 per)  1 week 50\begin{array} { c l l } \text { Deluxe Easter Basket BOM } & \text { Lead Time } & \text { On-Hand } \\\hline \text { Deluxe Easter Basket } & 1 \text { week } & 10 \\\text { Dark Chocolate Truffles (2 per) } & 2 \text { weeks } & 30 \\\text { Carved Chocolate Eggs (4 per) } & 1 \text { week } & 50\end{array} Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs; additionally one bottle of Alka-Seltzer is included for those who overindulge. When should an order for carved chocolate eggs be released?


A) at the start of week 2
B) at the start of week 3
C) at the start of week 4
D) at the start of week 5
E) at the start of week 6

F) B) and C)
G) A) and C)

Correct Answer

verifed

verified

Showing 61 - 80 of 89

Related Exams

Show Answer