The first unit of a product took 900 hours to build and the learning curve is 90%.How long will it take to make the first 3 units? (Use Table E.3 in the text. )


A) less than or equal to 2,470 hours
B) from 2,470 to 2,472 hours
C) from 2,472 to 2,475 hours
D) from 2,475 to 2,478 hours
E) from 2,478 to 2,481 hours

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

If the learning curve for a process is 100%,then each unit in a series of units will have the same labour requirements.

A) True
B) False

Correct Answer

verifed

verified

True

The arithmetic approach (or successive doubling approach)to learning curve calculations allows us to determine the hours required for any unit.

A) True
B) False

Correct Answer

verifed

verified

You are about to undertake manufacture of a labour-intensive electronics component.The first unit took 300 hours.You are not sure whether the learning rate is 70% or 80%.The initial phase of the contract calls for 6 of these components. a.How much time will it take to complete all six at 70% learning? b.How much time will it take to complete all six at 80% learning?

Correct Answer

verifed

verified

From Table E.3 in the text,70%...

View Answer

Which of the following statements comparing learning curve rates (L) to improvement rates is true?


A) The learning rate is the same as the improvement rate.
B) The learning rate is a decimal value while the improvement rate is a percentage.
C) A 90% learning curve corresponds to a 10% rate of improvement.
D) Learning rates apply to labour only,while improvement rates apply to all resources.
E) "Learning rates" is American usage,while "improvement rates" is British.

F) None of the above
G) A) and C)

Correct Answer

verifed

verified

In the logarithmic approach formula to compute the time for the Nth unit,TN = T1Nb,the exponent b is the learning curve rate L,expressed as a decimal.

A) True
B) False

Correct Answer

verifed

verified

Why do different organizations have different learning curves?

Correct Answer

verifed

verified

The rate of learning varies de...

View Answer

Experience curves are the opposite of learning curves-as one rises,the other falls.

A) True
B) False

Correct Answer

verifed

verified

False

Your firm has a contract to make 20 specialty lenses for night vision equipment.The first one took 40 hours.Learning is expected at the 85% rate.How long will it take to finish all 20 units?

Correct Answer

verifed

verified

The best solution method uses ...

View Answer

A certain product under development took 200 hours for the production of its 2nd unit and 180 hours for its 4th unit. a.What is the learning rate? b.How much time did the first unit take? c.How much time would the production of the 10th unit take? (Use both the logarithmic and the Table E.3 (in the text)approach.Do the two versions agree?)

Correct Answer

verifed

verified

(a)90%; (b)222.2 hours; (c)T10...

View Answer

Which one of the following statements about learning curves is true?


A) A learning curve assumes that the direct labour requirements per unit will DECREASE at an INCREASING rate as cumulative production increases.
B) A larger learning curve rate implies faster (greater) learning.
C) A learning curve graph usually follows a negative exponential curve.
D) Learning curves can be used only for individuals,not for the whole organization.
E) A lower learning curve rate implies weakness in learning.

F) None of the above
G) A) and C)

Correct Answer

verifed

verified

Which of the following statements regarding the usefulness of learning curves is false?


A) An external use of learning curves is in supply-chain negotiations.
B) A strategic use of learning curves is in evaluating company and industry performance.
C) An internal use of learning curves is in establishing costs.
D) An internal use of learning curves is in labour forecasting.
E) A strategic use of learning curves is in establishing budgets.

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

A manager is trying to estimate the appropriate learning curve for a certain job.The manager notes that the first four units had a total time of 30 minutes.Which learning curve would yield approximately this result if the first unit took 9 minutes? (Use Table E.3 (in the text) cumulative coefficient. )


A) 0.70
B) 0.75
C) 0.80
D) 0.85
E) 0.90

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

On an ordinary graph,unit times decrease at a decreasing rate,but on a log-log graph,the learning "curve" appears as a straight line.

A) True
B) False

Correct Answer

verifed

verified

Explain how learning curves might be applied in a bid preparation application.

Correct Answer

verifed

verified

Learning curves can determine the reduct...

View Answer

Explain how learning curves might be applied in a scheduling application.

Correct Answer

verifed

verified

Learning curves can determine the total ...

View Answer

The first unit of production took 10 hours with an 80% learning curve.How long will it take to complete both the first and second units?


A) 10 hours
B) 8 hours
C) 18 hours
D) 9 hours
E) There is not enough information to solve the problem.

F) B) and C)
G) All of the above

Correct Answer

verifed

verified

C

To use the table of learning curve coefficients,you must specify the ________ and the ________.

Correct Answer

verifed

verified

learning r...

View Answer

Learning curves are


A) the same for all products but different for different organizations.
B) the same for all organizations but different for different products.
C) the same for all organizations and all products.
D) different for different organizations and different products.
E) appropriate in services but not in manufacturing.

F) C) and D)
G) A) and D)

Correct Answer

verifed

verified

If the learning rate for a process is 80%,that same process has a 20% ________.

Correct Answer

verifed

verified